CORPORATE
AWARDS
Fond du Lac Water Control Facility
Elkhorn Rd Reconstruction/Bluff Rd
Reconstruction
Joliet Radium Compliance & System
Improvement Project
Open Road Tolling Plaza 66 & Plaza 69
Aux Sable Wastewater Treatment Plant
Greater Bayfield WWTP
Mount Horeb Roundabouts
US 421
Trek Bicycle Corporation Expansion
Janesville Pump Station No. 12
UW-Madison Angler's Cove
127th Street Over IAIS/Metra Railroad
Jackson Water 2000 North (Phase 7)
US 12 - Sauk City to Middleton
Wauponsee Glacial Trail
Channahon HMO Co-Filtration Plant
Algoma Water System
Seymour Wastewater Treatment Plant
NEWS
CONFERENCES
 


Awards

Fond du lac water control facility - fond du lac, wi
2008 – ACEC WI Engineering Excellence Award

Strand completed facilities planning and designed a total renovation of the water pollution control facility serving the City of Fond du Lac and surrounding area.  The design population for Fond du Lac is 49,000 and the additional design population for the contributing area is 30,000.  The average daily design flow for the facility is 9.84 mgd and the projected BOD load is 22,500 pounds per day.  The major project drivers were new ammonia effluent limits and aging, outdated treatment and biosolids management processes.  Construction of the facilities began in October 2005 and is scheduled for completion by December 2008.  The existing facility is a pure oxygen activated sludge facility employing a Zimpro thermal sludge conditioning system for sludge management.

The major pollutant loads to the treatment plant are domestic in nature.  The design industrial flow is projected to be 1.75 mgd.  The major industries deal with metal products manufacturing and dairy processing.  Consequently, the total industrial BOD load to the plant is projected to be approximately 30 percent of the total plant load.  The plant will be an advanced secondary activated sludge facility with primary clarification, single-stage nitrifications, denitrification, separate storm flow clarification, and chemical phosphorus precipitation.  UV effluent disinfection will also be provided.

A unique aspect of this project was the reuse of existing facilities to provide storage and/or treatment of peak flows in excess of the 34 mgd hydraulic capacity of the final clarifiers.  Flows exceeding 34 mgd will be routed to the existing primary clarifiers that initially function as storage.  Once the excess flow primary clarifiers are full they provide primary treatment.  Flows receiving primary treatment then flow to the excess flow storage (existing aeration tanks) prior to recombining with the flows receiving biological treatment.  The combined flows receive UV disinfection.  There is sufficient storage in the existing facilities to provide up to 3 hours of storage at a sustained flow rate of 16 mgd. Activated sludge is wasted to the primary clarifiers for cothickening with primary sludge.  Approximately 28,500 pounds per day of blended primary sludge and secondary sludge are projected under average design conditions.  The thickened sludge is anaerobically digested in a thermophilic-mesophilic digestion (TPAD) system to achieve Class A biosolids.  The TPAD system includes two thermophilic digesters and two mesophilic digesters.  The system was designed with considerable flexibility to operate in series or parallel, as well as to convert to an all mesophilic mode of operation.

The TPAD system is fully functional.  The anaerobic digesters are hydraulically mixed with a pumped recirculation system.  Biosolids dewatering will be with two centrifuges.

Biogas generated from the digesters will be used to heat the digesters and provide a significant amount of building heat.  The facilities were designed to easily add microturbines or engine generators in the future.  The owner is investigating privatized, long-term disposal options for dewatered biosolids.

back to top

elkhorn road roundabout/bluff road reconstruction - whitewater, wi
2008 – Midwest Construction                                                                               2008 – APWA Public Works Project of the Year

The City of Whitewater is a community of approximately 14,000 residents located in northwest Walworth County, Wisconsin.  The City is also home to the University of Wisconsin-Whitewater.

The City has seen significant industrial and residential growth on its east side in recent years.  This growth was made possible through creation of a Tax Incremental Financing (TIF) district that helped fund street and utility improvements needed to support development in the area.  The TIF district boundary was amended to include a 14-acre redevelopment parcel that a local developer proposed for commercial development.  The development, known as East Town Market, is bordered on the north by Bluff Road and on the west by Elkhorn Road.  The proposed development is to include a grocery store, gas station/convenience store, restaurant, and other business and office space.

In addition, after decades of planning, the Wisconsin Department of Transportation (WisDOT) opened the US 12 Bypass around the south side of the city in 2005.  As a result of the bypass, the City anticipates additional commercial development along Elkhorn Road, which now serves as the main entrance to the east side of the city from the bypass.  The US 12 Bypass allowed several City streets formerly designated as US 12 to be redesignated as Business Highway 12.  However, Elkhorn Road was redesignated as WIS 59.  Given this designation, WisDOT required that a Traffic Impact Analysis (TIA) be prepared to address the impacts that the proposed East Town Market development would have on Elkhorn Road/WIS 59.

In early discussions with WisDOT, they indicated no driveway connections between Elkhorn Road and the proposed development would be allowed.  Further, due to the awkward geometry of the Elkhorn Road/Bluff Road intersection and the close proximity of the Clay Street/Elkhorn Road intersection (see Figures 1 and 2), WisDOT indicated that realignment of Bluff Road through the development, to align with Clay Street, would likely be required.

Strand Associates, Inc.®, was hired by the City to assist with the design and construction administration elements of this project.  To begin, Strand prepared a TIA based on planned land uses in the East Town Market development as well as other anticipated growth on the east side of the city and along WIS 59.  Traffic projections showed future traffic volumes approaching 19,000 vehicles per day, approximately 100 percent more than current volumes.  To accommodate these volumes, the TIA recommended realignment of Bluff Road through the development to intersect Elkhorn Road at the intersection of Clay Street.  Recommendations also included installation of traffic signals and construction of turn lanes at the new intersection.  The new intersection, with long, dual left turn lanes on the southbound leg, was quite large and would be expensive to build due to the amount of Elkhorn Road that would need to be reconstructed.

Strand then developed a roundabout as an alternative intersection design.  Although the roundabout had a larger footprint than the signalized intersection, it did not require construction of long turn lanes.  The roundabout required the Developer to dedicate more land as right-of-way, but the lack of turn lanes actually provided the Developer more flexibility in terms of site access.  The roundabout intersection also had an estimated construction cost approximately 20 percent less than the signalized intersection.  Other advantages of the roundabout design included traffic calming and an opportunity for aesthetic enhancement at the east entrance to the city. 

WisDOT indicated that construction of either the signalized intersection or the roundabout intersection would be acceptable.  However, with the signalized intersection, they would not allow the traffic signal equipment to be installed until traffic warrants were met.  Ultimately, the City and Developer agreed to construct the roundabout intersection.

The final project scope included construction of a new roundabout at the intersection of Elkhorn Road/Bluff Road and Clay Street.  Construction of the roundabout required reconstruction of approximately 600 feet of Elkhorn Road and 400 feet of Clay Street.  The project included complete reconstruction of 1,600 feet of Bluff Road east of the new roundabout.  New sanitary sewer, water main, and storm sewer extensions needed to serve the development were part of the project.  New street lighting and relocation/burial of several private utilities were also included. Strand prepared the plans and specifications for all of these improvements.

Elkhorn Road and the roundabout were constructed with concrete pavement to match the existing street construction.  Decorative stamped, colored concrete was used on the roundabout truck apron, splitter islands, and crosswalks.  The center island of the roundabout was landscaped to create an attractive entry to the east side of the city.  New street lighting was also installed.  

Bluff Road was reconstructed to convert it from a rural-section road to an urban street with storm sewer, curb and gutter, sidewalk, and asphalt pavement.  This portion of the project was particularly challenging due to the extent of the proposed street widening, flat terrain, high bedrock, and shallow utilities.  The western 600 feet of Bluff Road was realigned in coordination with the East Town Market development to intersect the new roundabout.  New street lighting was also installed along Bluff Road.

The final construction cost of the project was $837,000, approximately $44,000 under the bid amount.  Final completion of the project was on November 6, 2007, approximately 18 days after the Contractual completion date.

 

back to top

joliet radium compliance and system improvement project - joliet, il
2008 – ACEC IL Engineering Excellence Award                                                    2008 – APWA Southwest Branch Award

The City of Joliet’s initial plan to meet new radium regulations was to convert from their groundwater supply, containing naturally occurring radium, to a surface water supply.  When the surface water plan became cost prohibitive, the resulting project became one of the largest groundwater system upgrades in the United States, impacting every component in the water system including wells, well houses, transmission mains, treatment plants, and storage facilities. 

To remove radium from the groundwater, the City implemented an innovative, recently developed treatment technology using the addition of hydrous manganese oxide (HMO) to form manganese particles that adsorb radium.  These resulting particles are large enough to be collected on a conventional sand filter. 

The City of Joliet water system is not only one of the largest groundwater systems in the state, but is now the largest water system using HMO treatment, capable of treating 33 million gallons per day (mgd).

 

back to top

Open road tolling plaza 66 (dekalb) and plaza 69 (dixon) – il
2008 – ACEC Engineering Excellence Award

The Illinois Tollway initiated a multi-billion dollar Congestion Relief Program (CRP) in 2004 aimed at addressing congestion along then 274-mile tolled highway system and improving travel for millions of motorists everyday. As part of this program, the Illinois Tollway proposed the conversion of 20 existing barrier toll plazas along the mainline to a barrier-free Open Road Tolling (ORT) system Reconstructing the existing DeKalb and Dixon mainline toll plazas was an integral part of this program.

Strand Associates, Inc.®, was hired by the Illinois Tollway as the lead design firm for the reconstruction of the DeKalb Plaza and Dixon Plaza along the Reagan Memorial Tollway (I-88). The goals of these two reconstruction projects were to cost-effectively provide non-stop electronic Open Road Tolling (ORT) and include new plaza buildings, a connecting walkway, and manual lanes with attendant booths and canopies to relieve congestion and create a safer roadway while improving air quality.

In just 22 months, Strand was able to convert the existing Dixon and DeKalb plazas to ORT, accomplishing the Tollway’s reconstruction goals while providing cost-effective alternatives that maintained the original timeline. Key milestones during this project include:

• Completed Preliminary study and Design, which were performed    concurrently in order to meet the target project completion date, in less than eight months.
• Completed design of alternative buildings in less than three months, while saving approximately
$6 million over the prototype building design performed by others.
• Provided ORT to motorists at the Dekalb Plaza within three months of project start.

The DeKalb and Dixon plaza projects are examples of excellence in engineering because they:

• Saved $8.4 million over the original project budget.
• Enhanced neighboring communities by improving local stormwater-management systems.
• Improved local air quality and safety of the motoring public by reducing traffic congestion.
• Respected adjacent communities by adapting site and layout to meet local needs and traffic.

The success and the overwhelming acceptance by both the communities and the client illustrates the overall excellence of this project.

back to top

Aux sable creek Basin wastewater treatment plant and conveyance project – joliet, il
2008 – ACEC Engineering Excellence Award
2008 – APWA Public Works Project of the Year Award
2008 – Midwest Construction                                                 

Recognizing the Aux Sable Creek as a valuable water resource, the City of Joliet embarked on a major wastewater collection, treatment, and transport infrastructure project to serve a 26-square-mile area in the rapidly developing Aux Sable Creek watershed.

The project included 3,000 feet of 54-inch interceptor sewer, influent sanitary pumping station, and 24-inch forcemain; an effluent pumping station and 5.7 miles of 36-inch diameter force main to the DuPage River; and a unique cascade aeration structure with DO metering run by solar power and transmission of the DO data to the plant via the city-wide SCADA system. The wastewater treatment plant is rated at 3.2 mgd average and 10 mgd peak (expandable to 30 mgd peak).

The project included eight construction contracts with six contractors. Construction began in fall 2004 and plant was in full operation by December 2005. Total construction cost was $36.7 million.

back to top

Greater Bayfield Wastewater Treatment Plant – bayfield, WI
2007 – ACEC National Recognition Award
2007 – ACEC WI Engineering Excellence Grand Award and Best of State
2007 – APWA Wisconsin Chapter Public Works Project of the Year
2007 – The Daily Reporter and Wisconsin Builder Best of 2006 Award
2006 – Midwest Construction Best of 2006 - Award of Merit Environmental
2006 – Clean Water State Revolving Fund - Pisces Award Region 5

In 2000, the City of Bayfield and Pikes Bay Sanitary District (PBSD), hired Strand to perform a facilities plan, and it was found that one regional Greater Bayfield Wastewater Treatment Plant (GBWWTP) that would achieve a higher standard of treatment in an environmentally friendly way was the best alternative. Even before design was complete, the Great Lakes Protection Fund (GLPF) and the Wisconsin Department of Natural Resources (DNR) identified the GBWWTP as a “Demonstration Plant” that would showcase environmentally-friendly technologies. Together with the Army Corps of Engineers, the GLPF and the DNR provided 70 percent grant support for the project.


The GBWWTP applies oxidation ditch activated sludge technology with biological nitrogen and phosphorus removal, minimizing the use of chemicals. After clarification, cloth disk filters polish the effluent to well beyond typical DNR standards. High efficiency ultraviolet disinfection occurs before discharge to Lake Superior. Biosolids are managed with reed beds, which provide natural dewatering through transpiration, a very energy efficient technology that only requires sludge removal approximately every 7 years. A variety of additional features maximize the energy efficiency of the plant.  The GBWWTP has been online since January 2006, and it has consistently achieved its treatment goals, even from start-up.

Please visit the City of Bayfield's website and view the narrated slideshow

back to top

CTH ID Roundabouts – Mount Horeb, WI
2008 – ACEC Engineering Excellence Award
2007 – APWA Wisconsin Chapter Project of the Year Award

We were retained by the Village of Mount Horeb for design of the rapidly developing CTH ID corridor.  The project scope included a total of four multilane urban roundabouts in a 1.1-mile corridor between the US 18/151 interchange and Perimeter Street.  We provided all design and construction engineering for the $3.5 million project.  One of the most challenging aspects of the project was the construction staging and traffic control planning required to build the project.  Construction of the project was substantially completed in November 2006.  Extensive landscaping included in the project was completed in 2007.

back to top

US 421 – Indianapolis, IN
2007 – Indiana Partnership for Highway Quality Award

The project transformed a two-lane roadway with occasional turn lanes into a five-lane urban arterial including a continuous two-way left turn lane. This full-depth concrete roadway uses curb and gutter for storm drainage. Traffic is maintained during construction on this heavily used corridor by widening the existing pavement and building the new road in halves. Extensive work is also done to three major intersecting roadways. The 106th, 116th, and 121st Streets were all widened and reconstructed with full-depth asphalt pavement with curb and gutter for drainage. Many cross structures have been designed for overland drainage including a three-sided bridge with architectural facing for aesthetics. Extensive utility coordination was required, as many utilities both private and municipal are located in this narrow corridor. Modular block, reinforced concrete and mechanically-stabilized earth retaining walls were used to save on right-of-way costs and to avoid home removals. For maintenance of traffic issues, 106th and 116th Streets are designed as signalized intersections using video detection. This allows the new signal to be fully actuated and not timed, as the cameras can be aimed wherever the traffic is located.

back to top

Trek Bicycle Corporation Expansion  – Waterloo, WI
2007 – The Daily Reporter and Wisconsin Builder Best of 2006 Award

Strand teamed up with Oliver Construction of Oconomowoc, WI. for the Trek Bicycle Corporation 78,000 s.f. expansion at their corporate headquarters in Waterloo, WI.  We provided survey, site/civil and structural engineering services.  The design features an exposed steel structure with a barrel arch over the lobby, relocation of all employee parking to a new 64,000 square foot parking lot, and design of a stormwater infiltration basin to accommodate the proposed site improvements.

back to top

City of Janesville Pumping Station No. 12 Nitrate Reduction Facility – Janesville, WI
2006 – APWA Wisconsin Chapter Project of the Year Award

In the Summer of 2001, the City of Janesville, Wisconsin, encountered rising nitrate levels in the City’s Well No. 7 was just below the maximum contaminant level for nitrates, which forcing the Water Utility to shut down the facility.   The Well No. 7 facility produced approximately half of the water consumed in the City’s south pressure zone.  Fortunately, the City had operational capabilities to allow the continued operation of the system while a solution was studied, planned and implemented.

The new Pumping Station No. 12 project consisted of a new 2,500 gpm well, 300,000-gallon, cast-in-place concrete mixing/dilution reservoir, 7,500 gpm booster station, modification of the existing 4,500 gpm shallow well pump, installation of standby power to improve reliability, 16-inch raw water connection main between Well No. 7 and Station No. 12, 20-inch discharge piping to the distribution system, and control integration into the existing SCADA system and security system.

Pumping Station No. 12 was constructed in vacated street right-of-way located between a City park and ice arena.  The roadway being used as a shortcut to bypass a local intersection.  This project eliminated the shortcut, while maintaining pedestrian traffic by adding a walking path.  This project successfully achieved its primary goal of providing a safe and reliable drinking water supply for the City of Janesville.  In addition, the project eliminated a public safety concern, used an underutilized property, and improved the efficiency of the water utility operation.

back to top

UW-Madison Angler's Cove Restoration – Madison, WI
2007 – DSF Excellence in Engineering Design Award
2006 – ACEC WI Engineering Excellence Honor Award

The University of Wisconsin-Madison is blessed with approximately 4.5 miles of lakeshore along Lake Mendota. With this blessing comes a responsibility to maintain and enhance the shoreline to control erosion, maintain aquatic and terrestrial habitat, and protect Lake Mendota.

To address the problems, Strand was hired to design a project that would convert the paved area back to its native dry prairie origins and provide an energy dissipater in the ravine to reduce velocities. In addition to these project elements, retaining walls were also designed to restore the original bluff character and a lake access structure constructed of environmentally-friendly Black Locust wood materials to route pedestrians away from the highly erodible bluff. To provide pedestrian an ADA-compliant limestone screenings walking path to route pedestrians along the top of bluff and from the parking area to the lake access structure that brings pedestrians down approximately 20 feet to the beach.

The overall eyesore has been restored to a jewel of the campus.

back to top

127th Street over iais/metra Railroad – blue island, IL
2006 – ACEC IL Engineering Excellence Special Achievement Award

The existing bridge carrying 127th Street over the Iowa Interstate Railroad and METRA Metropolitan Rail was determined by the Illinois Department of Transportation to be structurally deficient. As the corridor was designated a high accident location and the approach roadway was in poor condition, complete reconstruction of the roadway was included to enhance the corridor.

Improvements included: roadway reconstruction with new curb and gutter and sidewalks for the entire project area; new sewers, watermain, lighting, and signals. Bridge improvements include wider lanes and sidewalks, complete superstructure replacement, pier repairs, and abutment replacement.

Creative solutions were needed to meet all the goals of the project – Creative Design Measures Resulted in Accomplishing All Project Goals.

back to top

Jackson Water 2000 North (Phase 7) – Jackson, oh
2006 – ACEC OH Engineering Excellence Honor Award

The Jackson County Water Company, Inc. (JCWC) was incorporated in 1970 with 670 customers. Prior to the construction of this project, JCWC obtained potable water to supply its distribution system for its current 5,000 customers from several water producers within the region. As growth continued within the JCWC system and within the systems operated by the source water suppliers, it became apparent that the current raw water supply would not be adequate to meet the demand placed on it for the 21st century. This became the impetus for the largest water project funded by the USDA for Ohio.

Strand Associates, Inc.® was retained by JCWC to provide technical support for design, bidding, and construction of the new water production and treatment portion for the project.

Through cooperation among all entities involved with this project, JCWC is now poised to provide an adequate supply of high quality potable water to not only its existing customers but also to other areas residents well into the future beyond 2040.

back to top

US 12 – Sauk City to Middleton, WI
2005 – Midwest Construction Best of 2005 - Award of Merit Transportation

Wauponsee Glacial Trail – Forest Preserve District – Will County, IL
2005 – APWA National Project of the Year
2005 – APWA Chicago Metro and Southwest Branch Project of the Year Award
2004 – Midwest Construction Best of 2004 - Award of Merit Small Project
 

Channahon HMO Co-Filtration Plant – CHANNAHON, IL
2005 – ACEC National Recognition Award
2005 – ACEC IL Engineering Excellence Honor Award
2005 – APWA Southwest Branch of Chicago Metro Chapter Project of the Year Award

Algoma Water system – Town of Algoma, WI
2005 – ACEC WI Engineering Excellence State Finalist Award

Seymour Wastewater Treatment Plant, IN
2005 – ACEC IN Engineering Excellence Merit Award

back to top